The start of the building works. First a lockable store room to keep tools , bags of cement and anything else valuable . Toilet and shower block base and walls completed
-
-
The well has been dug to 80 ft to find water. The villagers are able to use the well.
-
-
Thefoundations for the first 2 classrooms started.
-
-
Deciding on the best site for the septic tanks behind the toilet /shower block.
-
-
The beginning of the septic tanks.
-
-
Store room completed and foundations fro clasrooms started.